Name of project |
: Ho Chi Minh road, section of La Son - Tuy Loan |
Representative of competent state agency |
: Ho Chi Minh Road Project Management Board |
Project enterprise |
: Cam Lo - Tu Loan BT Investment Limited Company |
Consulting on technical design |
: Truong Son Consulting Joint Stock Company |
Supervision consultants |
: DINVAI CUBA Company |
total investment |
: 11,486 billion dong. |
Implementation schedule |
: Construction started in February 2015 and expected to be completed in Q2 / 2018 |
Project's name: Ho Chi Minh road and La Son - Tuy Loan section in the form of BT contract
Representative of competent state agency: Ho Chi Minh Road Project Management Board
Project enterprise: BT Cam Lo - Tuy Loan Investment Co., Ltd.
Investor: Joint venture includes:
Supervision consultant: DINVAI CUBA Company.
Total investment: 11,486 billion dong.
Capital source: Invested capital and loan capital Tokyo Bank - Mitsumishi UFJ of Japan
Implementation progress: Commencement in February 2015, expected to complete in Quarter 2/2018
The La Son - Tuy Loan Expressway has the first point of La Son junction (Loc Son commune, Phu Loc, Thua Thien Hue) and the ending point in Tuy Loan (Hoa Vang district, Da Nang City), of which more than 11 km through Bach Ma National Park. The project is divided into 31 packages. By design, this highway is 77 km long, 22 m wide, with 4 lanes, total construction capital of nearly 11,500 billion. Phase 1 invested 2 lanes, phase 2 raised 4 lanes, cross section 23-24 meters wide, the allowed speed of 80km / h. Once completed, this route will run smoothly with the Danang - Quang Ngai expressway, shortening the travel time from Thua Thien - Hue to Quang Ngai.